Project update - April 2026

Our contractor was able to return to work at Hemsleys Meadow at the end of March and has made huge progress over the last month.
The drainage basins have been excavated. This has created a lot of soil which is currently in piles. Please be assured, these piles are temporary.
The Play Mound has been created using excavated subsoil, this will receive a thin layer of topsoil to take it up to a maximum height of 1.5m.