  • Project update - March 2026

    Share Project update - March 2026 on Facebook Share Project update - March 2026 on Twitter Share Project update - March 2026 on Linkedin Email Project update - March 2026 link
    supporting image

    Our contractor and MSDC officers continue to carry out weekly site inspections to closely monitor ground conditions. Over the past month, the site has been steadily drying out, and we’re now in a position to begin preparing for work to restart. Behind the scenes, arrangements are underway to remobilise the team, with the aim of returning to site w/c 30th March.

  • Work starting 15th October 2025

    Share Work starting 15th October 2025 on Facebook Share Work starting 15th October 2025 on Twitter Share Work starting 15th October 2025 on Linkedin Email Work starting 15th October 2025 link
    supporting image

    Our contractors, Blakedown Landscapes, will be on site from Wednesday 15th October 2025.

    These works are due to last approximately 21 weeks.

    The first part will be to complete the required ecological works. These works will involve setting up a reptile fence in Hemsleys Meadow and clearing the area inside of the fence.

    Hemsleys Meadow will be closed for the duration of the improvements. Access to most of Finches Field will be available but there may be changes in how you access the field.

    A storage, site office and welfare compound will be set up in Finches Field for the duration of the build.

    Have a look at the Post Planning consultation plan in the Plans and Documents section, to see what is going on.

    Check back here for updates!